STANDARD SPECIFICATIONS:
Polymer Modified
Asphalt Rubber Modified Slurry Seal
Back to Standard Specifications
List
Polymer modified slurry seal
is used in the same applications as a standard slurry seal however
polymer slurry seal has higher binder cohesion that leads to improvements
in resistance to raveling, especially in cul-de-sacs. Polymer modified
slurry seals are more abrasion resistant and can be laid at higher
application rates without bleeding or deformation. For airport application
suitable variations are made- including rolling.
1.01 SCOPE Slurry Seal shall consist of mixing asphalt emulsion,
aggregate, and water and spreading the mixture on a surface or pavement
where shown on the plans, as specified in these specifications and
the special provisions, and as directed by the Engineer.
2.01 MATERIALS
The materials for slurry seal immediately prior to mixing shall
conform to the following requirements:
2.02 (a) POLYMER MODIFIED ASPHALT EMULSION WITH CARBON BLACK
DISPERSION AND DISPERSED ASPHALT RUBBER.
The base polymer emulsified asphalt shall be a quick traffic,
quick cure (QT-QC) type, shall be a homogeneous brown color throughout
and show no separation after thorough mixing, shall break and set on
the aggregate within five (5) minutes and shall be ready for cross-traffic
within fifteen (15) to forty five (45) minutes. The polymer asphalt
emulsion, upon standing undisturbed for a period of twenty-four (24)
hours, shall show no white or milky colored substance on its surface
and conform to the requirements in Table I.
|
| TABLE I |
| Test on Emulsion | Method of Test | Requirement |
| Viscosity, SSF, @ 77 degrees F, sec | ASTM D244 | 15-90 |
| pH | | 1 to 3 |
| Distillation Residue %, Minimum | | 60 |
| Test on Residue from Distillation Test |
| Penetration, 77 degrees F., 100g, 5s | ASTM D5 | 40-80 |
| Softening Point (Ring & Ball), degrees F | ASTM | 130 + |
| Ductility, 77 degrees. F,(25C, 5 cm/Min., Minimum | ASTM D113 | 25 |
| Fraass-Breaking Point (degrees C.) min. | DIN 52012 | -18 |
|
Carbon black dispersion compatible with the emulsion shall be added by
suitable blending ( in line or propeller mixing) to the emulsion at
the plant before use. The carbon black at 30% solids by weight shall
be added at 6-8% on emulsion total weight.
A dispersion of asphalt rubber - RG-1 or equivalent - shall be blended
in line with the emulsion at the plant and the emulsion remixed before use.
This shall be added at 5-8% based on emulsion total weight.
The emulsion shall be mixed by circulation or other method before
pumping into the slurry truck.
2.02 (b) WATER
Water shall be potable, free of harmful soluble salts and shall be
of such quality that the asphalt will not separate from the emulsion
before the slurry seal is in place in the work.
2.02 (c) AGGREGATE
Aggregate shall consist of sound, durable, crushed stone or crushed
gravel and approved mineral filler. The material shall be free from
vegetable matter and other deleterious substances. Aggregates shall
be 100% crushed with no rounded particles. The percentage composition
by weight of the aggregate shall conform to the following grading:
|
| Percentage Passing |
| Sieve Sizes | Type II |
| 3/8"(9.5- mm) | 100 |
| No. 4(4.75- mm) | 90-100 |
| No. 8(2.36- mm) | 65-90 |
| No. 16(1.18- mm) | 40-70 |
| No. 30(600- um) | 25-50 |
| o. 200 (75- um) | N5-15 |
Theoretical asphalt content, % based on dry aggregate | 7.5-13.5 |
Approximate application rate (Pounds/Square Yard) | 14-18 |
|
The aggregate shall also conform to the following quality requirements:
|
| Test | Method of Test | Requirement |
Sand Equivalent or ASTM D2419 | California Method 217 | 60 Min. |
| Durability Index | California Method 229 | 55 Min. |
2.02 (d) POLYMER
Styrene Butadiene Rubber latex polymer shall be added to the water/soap
phase by injection prior to the mill manufacture of the asphalt
emulsion by the emulsion producer. The polymer shall be BASF NX 1118
or approved equal. The amount of polymer solids shall be between 3 and
4 percent of the asphalt residual content and shall be certified by the
emulsion producer on each load of emulsion delivered to the job site.
No post or field addition of polymer will be allowed. Samples of polymer
shall be provided and shall conform to the following requirements.
|
| Test | Requirement |
| Total Solids, min % | 60 |
| Bound Styrene % | 24 - 60 |
| pH at 25 Degrees C | 4.2 - 5.2 |
| Brookfield Viscosity RVT | 1000 - 4000 |
| Residual Monomer % | 0.08 max. |
2.02 (e) MINERAL FILLER
The mineral filler shall be either Portland Cement or other approved
mineral fillers, if required. Portland Cement if used, shall be
commercially available Type I-II and shall be free of lumps and clods.
2.03 MIX DESIGN
At least 7 working day before slurry seal placement commences, the
Contractor shall submit to the Engineer for approval a laboratory
report of tests and proposed mix design covering the specific materials
to be used on the project. The percentage of asphalt emulsion proposed
in the mix design shall be within the percentage range specified in Section
2.04 "Proportioning."
The tests and mix design shall be performed by a laboratory capable
of performing the applicable International Slurry Seal Association (ISSA)
tests. The proposed slurry seal mixture shall conform to the requirements
specified when tested in accordance with the following tests:
|
| Test | ISSA Test Method | Requirement |
| Slurry Seal Consistency, cm | T106 | 3 max. |
| Wet Stripping | T114 | Pass |
| Compatibility | T115 | Pass (a) |
| Cohesion Test, kg - cm within 1 hour | T139 | 20 min. (b) |
| Wet Track Abrasion, g/sq..ft. | T100 | 75 max. |
Immediately before commencing the slurry seal operations, all surface metal
utility covers (including survey monuments) shall be protected by thoroughly
covering the surface with an appropriate adhesive and paper or plastic.
No adhesive material shall be permitted to cover, seal or fill the joint
between the frame and cover of the structure. Covers are to be uncovered
and cleaned of slurry material by the end of the same work day.
Hand tools shall be available in order to remove spillage. Ridges or bumps
in the finished surface will not be permitted. The mixture shall be uniform
and homogeneous after spreading on the existing surface and shall not show
separation of the emulsion and aggregate after setting.
Adequate means shall be provided to protect the slurry seal from damage
from traffic until such time that the mixture has cured sufficiently so
that the slurry seal will not adhere to and be picked up by the tires of
the vehicles.
For the purpose of this project, the construction zone is defined to
include all stockpile staging areas and travel routes to/from streets
where the slurry seal is to be applied.
The Contractor shall abide, at all times, to the State of California,
Department of Transportation's "Manual of Traffic Controls for Construction
and Maintenance Work Zones" as applicable to this project.
Any deviations shall not be made without prior written approval from
the project engineer.
2.07 MEASUREMENT
Slurry seal will be measured and paid for by the square yard for the
actual surface areas covered.
2.08 PAYMENT
The contract price paid per square yard for slurry seal shall include
full compensation for furnishing all labor, materials, tools, equipment
and incidentals and for doing all the work involved in the furnishing and
placing of the slurry seal complete in place, including cleaning the surface
and protecting the slurry seal until it has set, all as shown on the plans,
as specified in these specifications and as directed by the Engineer.
|